SCHEDULES OF PLANNED PREVENTIVE MAINTENANCE CHECKLISTS

Planned Preventive Maintenance checklists , EASY AND READY TO BE DOWNLOADED , MODIFIED AND PRINTED MICROSOFT WORD DOCUMENTS W Weekly M Monthly Q Quarterly SA Semi/Annually A Annually SST Seasonal Start Up SSH Season Shut Down . No Registeration Needed!

EQUIPMENT DETAILS Chillers Monthly and Quarterly PREVENTIVE MAINTENANCE

Mannan

Administrator
Staff member
#1


proxy.php?image=http%3A%2F%2Fwww.sitei.net%2Fup%2Fdo.php%3Fimg%3D3&hash=ae866cb1b633706ea853d3841bcbc208


proxy.php?image=http%3A%2F%2Fwww.sitei.net%2Fup%2Fdo.php%3Fimg%3D4&hash=b63a662fc34192936ec29f3cd1a1fec2



الحمد لله والصلاة والسلام على رسول الله وعلى آله وصحبه أجمعين



EQUIPMENT DETAILS Chillers Monthly and Quarterly PREVENTIVE MAINTENANCE


SCHEDULE OF PLANNED PREVENTIVE MAINTENANCE Work Plan


SCHEDULES OF PLANNED PREVENTATIVE MAINTENANCE Work Plan


proxy.php?image=http%3A%2F%2Fwww.sitei.net%2Fup%2Fdo.php%3Fimg%3D135&hash=99e8149bc2db4bfef4b78228901a4731


EQUIPMENT DETAILS Chillers Monthly and Quarterly PREVENTIVE MAINTENANCE

صيانة دورية جداول جاهزة نظام بوابات الدخول المؤمنة

جاهزة للتحميل و سهلة التعديل و الطباعة مايكروسوفت وورد ملفات

EASY AND READY TO BE DOWNLOADED , MODIFIED AND PRINTED

MICROSOFT WORD DOCUMENTS TECHNICAL DATA SCHEDULES

Capacity
Qty: Lot
Make & Model

Location
Chillers Monthly and Quarterly PREVENTIVE MAINTENANCE


Task Description
W / Weekly M / Monthly Q / Quarterly SA/ Semi/Annually
A/ Annually SST / Seasonal Start/Up SSH / Season Shut Down
2W M 3M
6M A Notes

Item Description
Qty Notes

Critical Tasks to be performed Monthly

Lubricate Vane Linkage
Lubricate Motor Assembly
Lubricate Air compressor if there is pneumatic control
Inspect and clean the electrical panels and connections

Other recommended tasks Quarterly

Top-up thermometer pockets with oil
Oil filter cleaning oil pump function and current
Purge Unit filter cleaning For under pressure refrigerants
Check: Relief Valves, rupture discs for leaks
Test: Operation and safety cutouts, automatic controls and automatic devices for correct operation
Test: all gauges for correct reading calibrate if necessary

Notes
Use additional sheets if required
PPM routines based on Complete
Running hour where recommended by the Manufacturer


proxy.php?image=http%3A%2F%2Fwww.sitei.net%2Fup%2Fdo.php%3Fimg%3D6&hash=e694c7d9a3c445d7e5187539c644951d


http://www.sitei.net/up/do.php?id=136

or you can download from attachments
No registration required


! في أمان الله



proxy.php?image=http%3A%2F%2Fwww.sitei.net%2Fup%2Fdo.php%3Fimg%3D5&hash=acaedc343055116a139b8f0cbf6d6ab6


 

Attachments

Top