EQUIPMENT DETAILS Heating and Ventilation Units
SCHEDULE OF PLANNED PREVENTIVE MAINTENANCE Work Plan
EQUIPMENT DETAILS Heating and Ventilation Units
صيانة دورية جداول جاهزة المبادلات الحرارية
Capacity
Qty: Lot
Make & Model
Location
Heating and Ventilation Units
Consumable Spare Parts
Task Description
W / Weekly M / Monthly Q / Quarterly SA/ Semi/Annually
A/ Annually SST / Seasonal Start/Up SSH / Season Shut Down
2W M 3M
6M A Notes
Item Description
Qty Notes
Inspect entire unit for unusual noise and/or vibration, ensure that it is in good working order.
Provide lubrication, if necessary
Check that damper linkages are properly connected and operating
Inspect piping and fittings for leaks (steam, condensate, hot water, chilled water).
Inspect ductwork flexible connectors for abnormalities or leaks.
Inspect felt/rubber gaskets around access doors.
Following inspection, record observations and deficiencies, if any.
Check outside air intake louvers.
If problems are identified and unit requires servicing, perform all Non-Critical Tasks for the problematic components.
Inspect pre and final filters for abnormal accumulation of dirt and debris, replace if necessary.
Write installation date on new filters.
Clean filter rack and vacuum filter section after removal of old filters and prior to installing new filters.
Inspect filter rack and ensure that air path does not bypass filters.
Inspect coils (steam, hot water, chilled water) for accumulation of dirt and debris, clean if necessary.
Inspect/adjust humidifier, if present
Check access doors for tightness.
Check fire smoke dampers for proper operation.
Inspect belts for proper tension and wear
(if belts are replaced, record belt type and replacement date on unit)
Inspect entire motor and fan assembly, clean with a damp cloth.
Lubricate fan bearings and motors.
Lubricate all moving parts/connections, if necessary.
Operate dampers over the full modulation range, verify proper operation.
Inspect all gauges and meters, ensure they are functional, replace if necessary.
Inspect coil fittings, tighten if necessary.
Utilize fin comb to straighten coil fins.
Clean/flush water or y-strainers and drip leg.
Inspect steam traps
Inspect all fan wiring for deterioration.
Tighten all electrical contacts.
Inspect motor starter/control center.
Verify operation of starter and inspect contact surfaces for pitting or wear.
Check damper linkage, set screws and blade adjustment for proper tightness.
Inspect bearing collar set screws on fan shaft, ensure tightness.
Inspect fan and motor sheaves for proper alignment.
Notes
Use additional sheets if required
PPM routines based on Complete
Running hour where recommended by the Manufacturer